Wake County Superior Court judge upholds ruling by administrative law judge, orders agency to issue decision on Alcoa application within 30 days
Alcoa Power Generating Inc. (APGI) won a significant legal victory in Wake County Superior Court on Friday when a judge upheld a previous ruling that the N.C. Department of Environment and Natural Resources (DENR) wrongly denied a water quality certificate that is necessary to relicense the company’s dams along the Yadkin River.
Superior Court Judge Bryan Collins ruled that an administrative law judge was correct in finding that DENR exceeded its authority, acted erroneously and failed to act as required by law when it denied APGI’s application for a water quality certificate in August 2013. Judge Collins denied the state agency’s appeal and ordered DENR to reconsider APGI’s application and issue a decision within 30 days.
“We’re pleased the court has reaffirmed what we’ve known all along: the state had no legal reason to deny our application. We urge the state to follow the judge’s order and quickly issue a water quality certificate for the Yadkin Project,” said Ray Barham, APGI Relicensing Manager for the Yadkin Project.
Judge Collins notes that in the days leading up to DENR’s decision to deny APGI’s application, “DENR’s customary process of reasoned review collapsed under the pressure of 11th hour action by the Governor’s office and the (Department of Administration), agencies outside of DENR and having no direct responsibility for the protection of water quality or the environment.”
Before the Governor’s office inserted itself into the review process, Judge Collins says a final report recommended approving APGI’s application and issuing a water quality certificate for the Yadkin Project.
“DENR would have issued a merits based decision on the Application on August 2, 2013, likely issuing a 401 in APGI’s favor, but not for the secret intervention of the DOA and the Governor’s office into the process…” states Judge Collins ruling. “The undisputed facts recited in the Order demonstrate that DENR reversed course at the last minute, only after Executive Branch pressure and the 11th-hour filing of the Lawsuit.”
The NC Department of Administration filed a lawsuit against APGI on August 2, 2013, claiming ownership of the land under the Yadkin Project dams. The case is currently being considered in U.S. District Court by Judge Terrence Boyle.
The state’s failure to issue a water quality certificate has resulted in the unnecessary delay of water quality protections and improvements. APGI cannot move forward with its plans to invest up to $80 million on water quality improvements at the Yadkin Project until it receives a new federal license.
“We remain committed to meeting North Carolina water quality standards and have a proven solution to continue improving water quality at the Yadkin Project,” Barham said.
The issuance of a water quality certificate is a precondition to Federal Energy Regulatory Commission (FERC) issuing APGI’s new long-term license to continue generating clean, renewable energy at the Yadkin Project. FERC staff has previously recommended issuing a new license to APGI.
“We’re pleased the court has reaffirmed what we’ve known all along: the state had no legal reason to deny our application. We urge the state to follow the judge’s order and quickly issue a water quality certificate for the Yadkin Project,” said Ray Barham, APGI Relicensing Manager for the Yadkin Project.
Judge Collins notes that in the days leading up to DENR’s decision to deny APGI’s application, “DENR’s customary process of reasoned review collapsed under the pressure of 11th hour action by the Governor’s office and the (Department of Administration), agencies outside of DENR and having no direct responsibility for the protection of water quality or the environment.”
Before the Governor’s office inserted itself into the review process, Judge Collins says a final report recommended approving APGI’s application and issuing a water quality certificate for the Yadkin Project.
“DENR would have issued a merits based decision on the Application on August 2, 2013, likely issuing a 401 in APGI’s favor, but not for the secret intervention of the DOA and the Governor’s office into the process…” states Judge Collins ruling. “The undisputed facts recited in the Order demonstrate that DENR reversed course at the last minute, only after Executive Branch pressure and the 11th-hour filing of the Lawsuit.”
The NC Department of Administration filed a lawsuit against APGI on August 2, 2013, claiming ownership of the land under the Yadkin Project dams. The case is currently being considered in U.S. District Court by Judge Terrence Boyle.
The state’s failure to issue a water quality certificate has resulted in the unnecessary delay of water quality protections and improvements. APGI cannot move forward with its plans to invest up to $80 million on water quality improvements at the Yadkin Project until it receives a new federal license.
“We remain committed to meeting North Carolina water quality standards and have a proven solution to continue improving water quality at the Yadkin Project,” Barham said.
The issuance of a water quality certificate is a precondition to Federal Energy Regulatory Commission (FERC) issuing APGI’s new long-term license to continue generating clean, renewable energy at the Yadkin Project. FERC staff has previously recommended issuing a new license to APGI.
No comments:
Post a Comment